Warrior Met Coal, Inc.
HCC · United States · 1 operating model
US$89.94 × 52.9m diluted shares
Coverage average 4.4%
Risked NAV · US$5,389m
Asset P / NAV 0.88× Enterprise value ÷ attributable project NPV. Excludes corporate G&A, cash, debt and financing, so it compares across peers.
Unrisked 0.88×
Risked NAV / diluted share
Unrisked US$101.93 / share
Enterprise value US$4,599m
Accounting EBITDA US$708m
179 Mt attributable saleable reserves
Investment case
Valuation gap
The market is pricing the company at 0.88× risked NAV, with +13.3% to the modeled per-share value.
Portfolio concentration
Mines No. 4, No. 7 & Blue Creek is the largest modeled value driver at 100% of positive project NAV.
Risk cost
Jurisdiction, permitting and project risk reduce unrisked value by US$0m before the equity bridge.
Price versus modeled value
Production and sustaining FCF
Sustaining free cash flow after tax and production, both at the company's ownership share.
12 Mt peak attributable production
11.8% 2026E FCF yield
US$156m net cash entering the model
Cash flow statement
Attributable to Warrior Met Coal, Inc. shareholders. Each mine is modeled at 100%, including royalties and taxes, then included at the company's ownership share, so minority and government interests are already excluded.
| USD millions, except percentages and per-unit data | FY26 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | 2034 | 2035 |
|---|---|---|---|---|---|---|---|---|---|---|
| 12.2 | 12.2 | 12.2 | 12.2 | 12.2 | 12.2 | 12.2 | 12.2 | 12.2 | 12.2 | |
| US$2,158m | US$2,158m | US$2,158m | US$2,158m | US$2,158m | US$2,158m | US$2,158m | US$2,158m | US$2,158m | US$2,158m | |
| US$1,225m | US$1,225m | US$1,225m | US$1,225m | US$1,261m | US$1,261m | US$1,261m | US$1,261m | US$1,261m | US$1,261m | |
| US$145m | US$145m | US$145m | US$145m | US$145m | US$145m | US$145m | US$145m | US$145m | US$145m | |
AISC (US$/t) | 120.8 | 120.8 | 120.8 | 120.8 | 123.8 | 123.8 | 123.8 | 123.8 | 123.8 | 123.8 |
G&A | US$55m | US$55m | US$55m | US$55m | US$55m | US$55m | US$55m | US$55m | US$55m | US$55m |
| US$708m | US$708m | US$708m | US$708m | US$672m | US$672m | US$672m | US$672m | US$672m | US$672m | |
Depreciation & depletion | US$195m | US$203m | US$211m | US$221m | US$231m | US$243m | US$255m | US$270m | US$286m | US$306m |
| US$513m | US$505m | US$497m | US$487m | US$441m | US$430m | US$417m | US$402m | US$386m | US$366m | |
Interest expense | US$12m | US$12m | US$12m | US$0m | US$0m | US$0m | US$0m | US$0m | US$0m | US$0m |
| US$501m | US$493m | US$484m | US$487m | US$441m | US$430m | US$417m | US$402m | US$386m | US$366m | |
| US$155m | US$153m | US$151m | US$148m | US$136m | US$133m | US$130m | US$126m | US$122m | US$117m | |
| US$346m | US$340m | US$334m | US$339m | US$305m | US$296m | US$287m | US$276m | US$264m | US$250m | |
| US$110m | US$110m | US$110m | US$110m | US$110m | US$110m | US$110m | US$110m | US$110m | US$110m | |
| US$63m | US$0m | US$0m | US$0m | US$0m | US$0m | US$0m | US$0m | US$0m | US$0m | |
| US$560m | US$599m | US$419m | US$572m | US$530m | US$532m | US$534m | US$506m | US$474m | US$474m | |
| 11.8% | 12.6% | 8.8% | 12% | 11.1% | 11.2% | 11.2% | 10.6% | 10% | 10% | |
| US$235m | US$562m | US$368m | US$470m | US$406m | US$382m | US$358m | US$317m | US$277m | US$259m | |
Cash | US$524m | US$1,123m | US$1,385m | US$1,958m | US$2,487m | US$3,020m | US$3,554m | US$4,060m | US$4,534m | US$5,008m |
EV | US$4,388m | US$3,789m | US$3,370m | US$2,798m | US$2,268m | US$1,736m | US$1,201m | US$695m | US$221m | −US$253m |
Spending details
All-in cost per metre needs a disclosed cost or matching spend and metres for the same program and period.
NAV by asset
Mines, 2026 attributable
Metric tonnes; US$/t. Cash cost includes rail and port where reported FOB.
| Mine | Product | Own | Saleable Mt | Cash cost | Royalty | Sustaining | Margin | Reserves Mt | Life to | NPV US$m |
|---|---|---|---|---|---|---|---|---|---|---|
| Mines No. 4, No. 7 & Blue Creek | Mine No. 7 low-vol HCC plus Mine No. 4 and Blue Creek High Vol A | 100% | 12.2 | $100 | $12 | $9 | $55 | 179.3 | 2040 | 5,233 |
| Total | 12.2 | $100 | $9 | $55 | 5,233 |
Benchmark to realised price, 2026
Spot case · US$ per metric tonne.
| Mine | Benchmark | Index | Realised | Realised % | Quality / basis |
|---|---|---|---|---|---|
| Mines No. 4, No. 7 & Blue Creek | PLV HCC | $271 | $176 | 65% | 10.0% ash · 0.78% S · 29.3% VM · Q2 2026 average net selling price of US$151.91/t is the study anchor; market scenarios use price_benchmark x realisation_ratio. |
| Company | $271 | $176 | 65% |
Production
Attributable production by mine
AISC by mine
Life-of-mine average · excludes corporate G&A
1 covered assets
Attributable economics on the spot case.